At last Scottish Water are doing something tangible. They are upgrading the wastewater network at Dalreoch in Dumbarton to improve the environment on the River Leven by reducing spills and preventing sewer-related debris from entering the environment.

The work is part of the £500m Improving Urban Waters programme.

They claim to be preventing sewer debris from entering the environment

The high flats area of West Bridgend next to the polluted River Leven and the Artizan Bridge.

The project will reduce spills and prevent sewer-related debris from entering the environment during periods of heavy rain, such as we had at the weekend in West Dunbartonshire.

They are installing new pipework to carry wastewater flows to a new storm overflow chamber which will be fitted with a powered mesh screen preventing anything larger than 6mm from entering the water environment during periods of heavy rainfall.

The new storm overflow is being located under the overflow car park of Dalreoch railway station to allow the car park to remain partially open during construction to minimise impact on rail users.

The new chamber and outfall will replace the existing ones, which are located under the Dennystown Forge Metal Recycling scrapyard. These will be decommissioned.

The new overflow will be installed underneath the car park.  The work is part of the Improving Urban Waters programme

A spokesperson said: “The current storm overflow has been identified as a high priority for replacement by Scottish Water and the Scottish Environment Protection Agency (SEPA).

“Under the banner ‘Draining the Rain, Enhancing the Environment ’, the Improving Urban Waters investment will help reduce spills and prevent sewage-related debris such as wet wipes from entering the environment during periods of rainfall.

The main car park at Dalreoch railway station will remain open throughout the project.

Scottish Water claim work is progressing well on site, and they are now moving on to phase 3 of their programme, which involves installing a new section of sewer pipeline beside Glasgow Road (Cardross Road and the Artizan Bridge).

To allow them to carry out this work safely, a lane closure will be in place on the eastbound carriageway of Glasgow Road, including the Artizan Bridge, at its junction with Cardross Road between Renton Road and the entrance to the Dalreoch Station car park.

Five-way temporary traffic lights will also be in place on Glasgow Road, West Bridgend, Renton Road and the access road to the train station car park. These will be manned between 7am-7 pm, seven days a week, to help with the flow of traffic, about which residents of Dumbarton’s West End have been complaining long and hard for many months.

Scottish Water claim have worked hard to reduce the duration of this phase of their work to bring the programme forward.

Traffic management is now expected to be removed on Monday 7 December, ahead of the Christmas period, helping to minimise disruption for residents and road users.

The main car park at Dalreoch Station will remain open throughout the works; however, the lower car park will remain closed.  Advance signage is already in place in the area.

“We would like to thank the local community for their patience and understanding while we complete this essential investment,” the Scottish Water spokesperson said.