State-owned shipyard ‘blocked’ from bidding for new CalMac ferry …

A black and white ship with red funnelsA concept design drawing for the ship that will replace MV Lord of the Isles on the route between Mallaig and Lochboisdale on South Uist.

by Calum Watson for BBC Scotland

BBC Scotland

Scotland’s publicly-owned shipyard across the Clyde at Post Glasgow says it has been blocked from bidding to build the next large CalMac ferry.

Ferguson Marine said it was unable to bid to build a replacement for MV Lord of the Isles because eligibility rules set by ferries procurement agency, Caledonian Maritime Assets Limited (CMAL) have, in effect, excluded UK shipbuilders.

The GMB union said it “beggars belief” and called on the board of CMAL – which is owned by Scottish ministers – to pause and review the tendering process

CMAL said it had chosen a selection system which it believed would ensure the best outcome for island communities.

Shipyards are not automatically allowed to bid for taxpayer-funded ship orders in Scotland.

First they have to complete a Single Procurement Document Scotland (SPDS) – a questionnaire asking about things like financial status, capability and previous experience.

CMAL then draws up a shortlist of about six firms which are invited to tender detailed bids for evaluation.

The latest SPDS asks for a minimum of two examples of ships longer than 75m delivered by the shipyard in the past five years, but this does not include ongoing projects – something which was allowed in previous procurement.

Ferguson Marine delivered MV Glen Sannox in November 2024 but a second large CalMac ferry MV Glen Rosa is not due for delivery until the end of this year.

UK shipyards ‘at a disadvantage’

Ferguson Marine has now confirmed it will not submit a bid for the Lord of the Isles replacement vessel because of CMAL’s eligibility criteria and the lack of “social value” scoring in the evaluation process.

Chief executive Graeme Thomson said: “While we were eager to bring this project back to the Clyde, a rigorous review of the tender prequalification criteria indicates that, in our view, it is unlikely that any UK shipbuilder would meet the stipulated minimum qualification requirements.

“The original vessel was built here at Ferguson’s and has served the CalMac fleet for 36 years, a testament to the enduring quality of Scottish craftsmanship.

“However, without a procurement model that scores UK social and economic value and builds domestic supply chain resilience, which is in line with government nationwide guidance, UK shipyards remain at a disadvantage against heavily subsidised foreign competitors.”

BBC Scotland News reported earlier this month that social value scoring would not be part of CMAL’s evaluation and that “community benefits” would only be negotiated after a preferred bidder was named.

A woman with white hair, large silver earrings and wearing a white blouse, staring at the cameraThe GMB’s Louise Gilmour said the procurement process seemed designed to ensure shipbuilding orders went overseas

The GMB, the main trade union representing Ferguson workers, called on CMAL to “urgently pause” the tendering process and explain why Ferguson’s and other UK yards have been “effectively blocked from bidding”.

GMB Scotland general secretary Louise Gilmour said: “It beggars belief that a Scottish public body would bar a publicly-owned Scottish shipyard from even bidding to build a Scottish ferry.”

She added: “There could not be a clearer example of the self-harming procurement policies that have sabotaged our country’s industrial capability and economic growth for too long.

“There can be no other country in the world as happy to send contracts abroad instead of using them to support jobs, apprenticeship and communities at home.

“Taxpayers deserve value for money but the bottom line of any bid means nothing if the social and economic value to our communities is not properly taken into account.”

CMAL defended the wording of the questionnaire, and is understood to have turned down a request to modify it.

A spokesperson said: “The questions in the SPDS (Single Procurement Document Scotland) have been designed to ensure the best outcome for island communities.”

A black and white ferry with red funnels and Caledonian MacBrayne written on the sideMV Lord of Isles originally served the Coll/Tiree, Barra/South Uist routes.

While delays and overspends with the dual-fuel ships MV Glen Sannox and MV Glen Rosa are well documented, the GMB has argued that the smaller and less complex Lord of the Isles replacement vessel is a good fit for Ferguson’s capabilities.

Both the union and the shipyard had asked for a direct award of the contract.

This was rejected in March, although Scottish ministers signaled an intention to directly award four other vessels in future if they remain in power.

Ferguson’s, founded in 1903 and now the last remaining shipyard on the lower Clyde, has built about half of CalMac’s current large vessels fleet, including the existing Lord of the Isles, known as Loti, in 1989.

Since the early 2000s, however, it has struggled to compete on cost with overseas competitors in countries like Poland and Turkey.

While it has plans to raise productivity with promised investment including a new semi-automated plating line, the firm faces a potential order gap next year after delivery of Glen Rosa.

A collection of grey industrial buildings with a yellow crane and a large ferry docked at the quaysideFerguson Marine is the last shipyard on the lower Clyde

Last year the Society of Maritime Industries told MPs that a combination of better state support, tax breaks and lower labour costs typically allowed overseas shipyards to undercut UK yards by 10-20%.

The UK’s National Shipbuilding Strategy has called for social value – things like training and supply chain benefits – to be scored as part of publicly-funded orders, in order to give UK shipbuilders a better chance of winning contracts.

CMAL has rejected this, arguing it could conflict with its duties under Scottish procurement law which requires it to adhere to principles of “equal treatment” and “non-discrimination”.

CalMac ferries were among a 150 vessel, 30-year pipeline of potential orders listed in the 2022 refresh of the National Shipbuilding Strategy, external

But since then many of those vessels have gone to overseas shipyards.

A Ministry of Defence contract to provide 24 Royal Navy support vessels such as tugs was subcontracted to Serco which then gave the shipbuilding order to Dutch firm Damen.

An order for a new Northern Lighthouse Board vessel, Pole Star, went to Spain and CMAL has placed ferry orders worth about £570m with overseas companies in Turkey, Poland and China since 2022.

One comment

  1. Absolutely outrageous that the Scottish Government is promoting through CMAL the building of lifeline Scottish Ships in foreign lands.

    We should be building ships in Scotland for Scotland using local yards delivering jobs to people in Scotland. Fergusson Marine is a good yard with good workers and a good management.

    The problem in all of this is Caledonian Marine Assets Ltd or CMAL. They are an inefficient blimp of an organisation and the problem in all of the ship procurement is their poor design and specification of their requirements for ships and subsequent interference with the ship building yards.

    The recent delivery of the new MV Islay built in Turkey was the most recent example of CMAL ineptitude. It was delivered over one year late. And why was this, well CMAL tried to pass it off as being something to do with supply chain issues in Turkey. And then on its maiden voyage it took over four weeks to transit form Turkey to Scotland as opposed to the scheduled one week – due it was said to bad weather. Funny that the over a year delay, just like all the other CMAL ships and with the common denominator the CMAL designs.

    And so it was the the two ferries Glen Sannox and Glen Rossa, seven years late, £600 million over budget due to their world class CMAL design that is still not delivering. But do folks know about the three world class electric hybrid ferries built at three times the normal cost. One, the MV Hallaig had a big battery fire and was so world class that it couldn’t be fixed because the technology was out of date.

    The other two, plying the Clyde routes had to be pulled from service because of the risk of them going on too. New ferries, three times the price at £10m a pop and they don’t even last ten years. Well done their ” godmother ” who launched the first on in a fan fare.

    But hey hoe the poor suckers on the Scottish Islands relying on these lifeline ferries and the wider taxpayer just have to suck it up. Catamaran ships of proven design, used world wide could be built at a third of the cost but no. CMAL’s ineptitude and vested interests just go on and on.

    But its the same with regard to the huge offshore windfarm jackets. Are the made here in yards here. of course not Norway, Dubai and China.. At least when we found oil the rigs were built here. But yes, why would you build offshore wind jackets here.

    Not difficult to see why Scotland is a burst ball. Training, skills, industrial infrastructure all gone and going the way of a third world country on the edge of Europe. Ah well, but who needs jobs when we are Scotland the Great – eh?

Leave a Reply